Details

Reactor Type Boiling Water Reactor (or BWR)
Model BWR-3
Owner The Chugoku Electric Power Co., Inc.
Operator The Chugoku Electric Power Co., Inc.

Timeline

Construction Start Thursday, 2 July 1970
First Criticality Friday, 1 June 1973
First Grid Connection Sunday, 2 December 1973
Commercial Operation Friday, 29 March 1974
Long-term Shutdown Monday, 8 November 2010
Permanent Shutdown Thursday, 30 April 2015

Specifications

Capacity Net 439 MWe
Capacity Gross 460 MWe
Thermal Capacity 1380 MWt
Design Net Capacity 439 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
1973 439 430 43.00 - - - - -
1974 440 7279 3006.40 88.50 86.70 86.70 88.00 88.00
1975 439 7010 2946.10 80.00 78.70 82.10 76.60 81.50
1976 439 6697 2802.90 76.20 72.70 78.70 72.70 78.30
1977 439 4489 1879.10 51.20 48.90 70.80 48.90 70.50
1978 439 6394 2701.80 73.00 70.30 70.70 70.30 70.40
1979 439 6341 2623.60 72.40 68.40 70.30 68.20 70.00
1980 439 6466 2734.60 73.60 70.90 70.40 70.90 70.20
1981 439 5430 2293.10 62.00 57.00 68.60 59.60 68.80
1982 439 5499 2366.80 62.80 61.50 67.80 61.60 68.00
1983 439 6268 2696.10 71.60 70.10 68.00 70.10 68.20
1984 439 6912 2990.69 78.70 78.20 69.00 77.60 69.10
1985 439 8705 3790.40 99.40 99.10 71.60 98.60 71.60
1986 439 4903 2130.53 56.00 55.50 70.30 55.40 70.30
1987 439 6937 3011.22 79.20 78.60 70.90 78.30 70.90
1988 439 5398 2355.11 61.40 61.10 70.20 61.10 70.20
1989 439 5965 2616.31 68.10 68.10 70.10 68.00 70.10
1990 439 8565 3745.51 97.80 97.40 71.70 97.40 71.70
1991 439 7123 3111.32 81.30 80.90 72.20 80.90 72.20
1992 439 6134 2671.29 69.80 69.40 72.10 69.30 72.10
1993 439 5849 2549.09 66.80 66.50 71.80 66.30 71.80
1994 439 6733 2948.02 76.90 76.70 72.00 76.70 72.00
1995 439 6862 2984.63 78.30 78.00 72.30 77.60 72.30
1996 439 5154 2245.47 58.70 58.40 71.70 58.20 71.70
1997 439 6712 2923.56 76.60 76.20 71.90 76.00 71.80
1998 439 8760 3845.36 100.00 100.00 73.00 100.00 73.00
1999 439 7657 3359.32 87.40 87.40 73.60 87.40 73.50
2000 439 3149 1381.16 35.80 35.80 72.20 35.80 72.10
2001 439 6488 2844.61 74.10 74.00 72.20 74.00 72.20
2002 439 7730 3393.22 88.20 88.20 72.80 88.20 72.80
2003 439 6253 2748.99 71.40 71.40 72.70 71.50 72.70
2004 439 8784 3937.86 100.00 100.00 73.60 102.10 73.70
2005 439 5349 2382.28 61.10 60.80 73.20 62.00 73.30
2006 439 6025 2699.47 68.80 68.80 73.10 70.20 73.20
2007 439 6441 2866.64 73.50 73.40 73.10 74.50 73.20
2008 439 6142 2738.45 69.90 69.70 73.00 71.00 73.20
2009 439 5667 2533.19 64.70 64.40 72.80 65.90 73.00
2010 439 2151 969.91 24.60 24.50 71.40 25.20 71.70
2011 439 0 0.00 0.00 0.00 69.60 0.00 69.80
2012 439 0 0.00 0.00 0.00 67.80 0.00 68.00
2013 439 0 0.00 0.00 0.00 66.00 0.00 66.30
2014 439 0 0.00 0.00 0.00 64.40 0.00 64.60
2015 439 0 0.00 0.00 0.00 63.90 0.00 64.10

Source: Operating details - IAEA PRIS