Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | VVER V-412 |
Owner | Nuclear Power Corporation Of India Ltd |
Operator | Nuclear Power Corporation Of India Ltd |
Timeline
Construction Start | Thursday, 4 July 2002 |
---|---|
First Criticality | Sunday, 10 July 2016 |
First Grid Connection | Monday, 29 August 2016 |
Commercial Operation | Friday, 31 March 2017 |
Specifications
Capacity Net | 932 MWe |
---|---|
Capacity Gross | 1000 MWe |
Thermal Capacity | 3000 MWt |
Design Net Capacity | 917 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2016 | 917 | 1790 | 749.03 | - | - | - | - | - |
2017 | 932 | 4991 | 4147.80 | 50.20 | 48.60 | 48.60 | 45.80 | 45.80 |
2018 | 932 | 3846 | 2761.23 | 43.90 | 33.80 | 40.20 | 33.80 | 39.00 |
2019 | 932 | 8217 | 4573.82 | 93.80 | 56.10 | 46.00 | 56.00 | 45.20 |
2020 | 932 | 6446 | 5885.37 | 73.40 | 70.90 | 52.60 | 71.90 | 52.30 |
2021 | 932 | 6105 | 5537.43 | 69.70 | 67.20 | 55.70 | 67.80 | 55.60 |
2022 | 932 | 7079 | 6586.51 | 80.80 | 79.60 | 59.80 | 80.70 | 59.90 |
2023 | 932 | 6714 | 5988.25 | 76.60 | 72.20 | 61.70 | 73.40 | 61.90 |