Details

Reactor Type Pressurised Water Reactor (or PWR)
Model APR-1400
Owner Emirates Nuclear Energy Corporation
Operator Nawah Energy Company

Timeline

Construction Start Wednesday, 24 September 2014
First Criticality Thursday, 22 September 2022
First Grid Connection Saturday, 8 October 2022
Commercial Operation Friday, 24 February 2023

Specifications

Capacity Net 1337 MWe
Capacity Gross 1417 MWe
Thermal Capacity 3983 MWt
Design Net Capacity 1310 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2022 1337 1703 1189.53 - - - - -
2023 1337 7865 10442.83 97.70 96.80 96.80 97.70 97.70
Subscribe to receive updates on news